17.
The expected out turn of half brick partition wall per mason per day is
Discussion:
50 comments Page 2 of 5.
RaviG said:
9 years ago
In MCQ books the answer is 5.0 sq m.
Which is correct? Please tell.
Which is correct? Please tell.
Uttam Khanra said:
2 years ago
First, Half bricks partition wall will be in m2. It will be 7.5m2.
Roushan kumar said:
6 years ago
Answer D is correct. Calculate in meter square not in meter cube.
AWADHESH KUMAR VERMA said:
8 years ago
Answer D is correct.
Ref : B.N. DUTTA Estimating and Costing.
Ref : B.N. DUTTA Estimating and Costing.
Guarav said:
9 years ago
Yes, @Nity.
5 sq m or 50 Sqft is the correct answer.
5 sq m or 50 Sqft is the correct answer.
James said:
2 years ago
I think the correct answer, is option (d).
Rakesh Kumar said:
5 years ago
I too agree, D should be the right answer.
Bashishth Baitha said:
2 years ago
I think the correct answer is option D.
(1)
Alvin said:
9 years ago
Absolutely, the answer should be in m2.
Engr khan said:
3 years ago
Option D. 5 m^2 is the correct answer.
(1)