Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 7)
7.
In the given figure, the network of a project represents


Discussion:
12 comments Page 1 of 2.
Deepankar said:
4 years ago
B is wrong because there is no arrow-head that would tell which is a head event and which is tail event.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.
(3)
Shubham Anadkat said:
4 years ago
"Excavation Of Footing" indicates the Activity. So here no matter there is an arrow or not.
So according to me option C fulfill all criteria.
So according to me option C fulfill all criteria.
Sumit said:
9 years ago
B is wrong because no arrow sign. A and C is correct. But C gives both activity and time. So more accurate is c.
(2)
Harshil Jariwala said:
8 years ago
Activities are shown by arrows only. There is no arrow shown here. So, option D is the right answer.
Gulshan k said:
7 years ago
@Muhammad.
The digit written on an arrow represents the time required to complete that activity.
The digit written on an arrow represents the time required to complete that activity.
Dinesh said:
5 years ago
D is the correct answer. Because, Arrow indicates activity. Here no arrow, so no activity.
(1)
Muhammad Atiq said:
7 years ago
But how it take 8 units of time?
Can anyone explain this?
Can anyone explain this?
Hesham bendary said:
1 decade ago
A, B, C are correct. Anyone explain why answer is (C)?
Abdul samad said:
9 years ago
C is correct, it gives both the information.
Ravi said:
7 years ago
Thanks for the right information @Sumit.