Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 7)
7.
In the given figure, the network of a project represents
activity of an excavation of a footing
activity of an excavation which starts at event No. 1 and ends at even No. 2
activity of excavation which takes 8 units of time
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Bastenga said:   6 years ago
Right, Thanks @Sumit.

Rahul Agrahari said:   7 years ago
Thanks @Sumit.


Post your comments here:

Your comments will be displayed after verification.