In the given figure, the network of a project represents


Discussion:
12 comments Page 1 of 2.
Hesham bendary said:
1 decade ago
A, B, C are correct. Anyone explain why answer is (C)?
Sumit said:
9 years ago
B is wrong because no arrow sign. A and C is correct. But C gives both activity and time. So more accurate is c.
(2)
Abdul samad said:
9 years ago
C is correct, it gives both the information.
Harshil Jariwala said:
8 years ago
Activities are shown by arrows only. There is no arrow shown here. So, option D is the right answer.
Ravi said:
7 years ago
Thanks for the right information @Sumit.
Rahul Agrahari said:
7 years ago
Thanks @Sumit.
Muhammad Atiq said:
7 years ago
But how it take 8 units of time?
Can anyone explain this?
Can anyone explain this?
Gulshan k said:
7 years ago
@Muhammad.
The digit written on an arrow represents the time required to complete that activity.
The digit written on an arrow represents the time required to complete that activity.
Bastenga said:
6 years ago
Right, Thanks @Sumit.
Dinesh said:
5 years ago
D is the correct answer. Because, Arrow indicates activity. Here no arrow, so no activity.
(1)