Discussion Forum : Construction Management - Section 1 (Q.No. 7)
7.
In the given figure, the network of a project represents


Discussion:
12 comments Page 2 of 2.
Shubham Anadkat said:
4 years ago
"Excavation Of Footing" indicates the Activity. So here no matter there is an arrow or not.
So according to me option C fulfill all criteria.
So according to me option C fulfill all criteria.
Deepankar said:
4 years ago
B is wrong because there is no arrow-head that would tell which is a head event and which is tail event.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.