Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 7)
7.
In the given figure, the network of a project represents


Discussion:
12 comments Page 1 of 2.
Deepankar said:
4 years ago
B is wrong because there is no arrow-head that would tell which is a head event and which is tail event.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.
A is true but C gives more detail in addition to A. Thatss why it is preferred over A.
(3)
Shubham Anadkat said:
4 years ago
"Excavation Of Footing" indicates the Activity. So here no matter there is an arrow or not.
So according to me option C fulfill all criteria.
So according to me option C fulfill all criteria.
Dinesh said:
5 years ago
D is the correct answer. Because, Arrow indicates activity. Here no arrow, so no activity.
(1)
Bastenga said:
6 years ago
Right, Thanks @Sumit.
Gulshan k said:
7 years ago
@Muhammad.
The digit written on an arrow represents the time required to complete that activity.
The digit written on an arrow represents the time required to complete that activity.
Muhammad Atiq said:
7 years ago
But how it take 8 units of time?
Can anyone explain this?
Can anyone explain this?
Rahul Agrahari said:
7 years ago
Thanks @Sumit.
Ravi said:
7 years ago
Thanks for the right information @Sumit.
Harshil Jariwala said:
8 years ago
Activities are shown by arrows only. There is no arrow shown here. So, option D is the right answer.
Abdul samad said:
9 years ago
C is correct, it gives both the information.
Post your comments here: