For batching 1:3:6 concrete mix by volume, the ingredients required per bag of 50 kg cement, are:
Discussion:
22 comments Page 3 of 3.
Kapfoie said:
6 years ago
The Volume of 50kg bag of cement =35 litre,
Therefore;
Sand 35x3=105.
Aggregate 35x6=210.
Therefore;
Sand 35x3=105.
Aggregate 35x6=210.
(16)
Sabin said:
6 years ago
Guys I am a bit confused here. Isn't it kg and liters are equal? Then why not 50 kg of cement = 50 liters of cement?
(3)