Discussion Forum : Building Construction - Section 4 (Q.No. 4)
4.
The form work from the slabs excluding props, can be removed only after
1 day
4 days
7 days
14 days
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
17 comments Page 1 of 2.

Rajiv sinhmar said:   1 decade ago
My name is Rajiv sinhmar, a civil engg.

I think :- deshuttering mainly depend in two ways 1. Height of span 2. Climate condition (if we are cast the slab in summer season so that early deshutterig but if winter so that time period will be change). So that please suggest me in why take a decision for deshuttering in 4 days.

SHUBHAM SIDDHARTH NAYAK said:   4 years ago
For removal of formwork (without props).

Slab -3 days.

For removal of props.

Slab upto 4.5 m span- 7 days.
Slab more than 4.5 m span-14 days.
Hence as without props is 3 days.

So the nearest answer is 4 days.
And it is absolutely correct.
(2)

Vinod kumar kesari said:   1 decade ago
Dear Sir,

I am bit confused at which concept you have to take deshuttering made for slab within 4 days. Setting of concreting depend on environmental condition, span and thickness. But how it would be for 4 days only please explain.

Pushap raj said:   8 years ago
Deshuttering,( formwork, stripping) time.

Vertical side of beams and column 24- 48 hours.
Slab span upto 4.5 m 7 days.
Slab span 4.5 to 6 m 14 days.
Slab span over 6 m 21 days.

Younus said:   5 years ago
Prop means standards which resist comprehensive load and which supports slab & here the questions was except prop then we only left with side runners which could be removed after 1 day.
(1)

Honey said:   9 years ago
It's correct soffit formwork of slab can be removed after 3 days props should be refixed. Since 3 days is not in the option that's why 4 days is correct.

Mohamed moawad said:   10 years ago
I think for normal strength concrete at 10 days. For rapid strength concrete may be at 4 days.

Maari said:   9 years ago
@All.

I think, it is minimum no of days in the question. So the given answer is correct.

Ankit said:   4 years ago
Option C, 7 days is the right answer.
For spans less than 4.5 m.

Sahil Chavda said:   5 years ago
Slab excluding props -4 day.

Beam excluding props - 14 day.