4.
The form work from the slabs excluding props, can be removed only after
1 day
4 days
7 days
14 days
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
17 comments Page 1 of 2.

SHUBHAM SIDDHARTH NAYAK said:   4 years ago
For removal of formwork (without props).

Slab -3 days.

For removal of props.

Slab upto 4.5 m span- 7 days.
Slab more than 4.5 m span-14 days.
Hence as without props is 3 days.

So the nearest answer is 4 days.
And it is absolutely correct.
(2)

Sahil Chavda said:   5 years ago
Slab excluding props -4 day.

Beam excluding props - 14 day.
(1)

Younus said:   5 years ago
Prop means standards which resist comprehensive load and which supports slab & here the questions was except prop then we only left with side runners which could be removed after 1 day.
(1)

Akshay said:   6 years ago
What is the meaning of props?
(1)

Roy said:   8 years ago
3 days should be the correct answer.

Ankit said:   4 years ago
Option C, 7 days is the right answer.
For spans less than 4.5 m.

Pushap raj said:   8 years ago
Deshuttering,( formwork, stripping) time.

Vertical side of beams and column 24- 48 hours.
Slab span upto 4.5 m 7 days.
Slab span 4.5 to 6 m 14 days.
Slab span over 6 m 21 days.

Ahmed said:   8 years ago
14 days required is correct.

RANJIT CHAUHAN said:   8 years ago
That no specifiy soffit slab the correct answer is 7.

Rajiv sinhmar said:   1 decade ago
My name is Rajiv sinhmar, a civil engg.

I think :- deshuttering mainly depend in two ways 1. Height of span 2. Climate condition (if we are cast the slab in summer season so that early deshutterig but if winter so that time period will be change). So that please suggest me in why take a decision for deshuttering in 4 days.