Civil Engineering - Building Construction

1.
To stagger vertical joints in successive courses of a wall, a piece of brick is generally used at the end of the course, which is known as
bat
header
stretcher
closer.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

2.
The concrete slump recommended for foundations, is
25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

3.
The minimum thickness of walls built in cement mortar (1 : 6) for a single storey building, is
10 cm
15 cm
20 cm
25 cm
30 cm.
Answer: Option
Explanation:
No answer description is available. Let's discuss.

4.
The form work from the slabs excluding props, can be removed only after
1 day
4 days
7 days
14 days
Answer: Option
Explanation:
No answer description is available. Let's discuss.

5.
The pile provided with one or more bulles in its vertical shaft, is generally known as
under-ream pile
friction pile
bearing pile
sheet pile.
Answer: Option
Explanation:
No answer description is available. Let's discuss.