Civil Engineering - Building Construction - Discussion
Discussion Forum : Building Construction - Section 4 (Q.No. 4)
4.
The form work from the slabs excluding props, can be removed only after
Discussion:
17 comments Page 2 of 2.
Mahesh sinh said:
8 years ago
I think as per IS 456 it's 7 days.
Ashish Tadewar said:
8 years ago
4 days? How? Can anyone explain it clearly?
Honey said:
9 years ago
It's correct soffit formwork of slab can be removed after 3 days props should be refixed. Since 3 days is not in the option that's why 4 days is correct.
Maari said:
9 years ago
@All.
I think, it is minimum no of days in the question. So the given answer is correct.
I think, it is minimum no of days in the question. So the given answer is correct.
Krishan murari roy said:
10 years ago
Shuttering removing after 7 days under 4.5 meter in span.
Mohamed moawad said:
10 years ago
I think for normal strength concrete at 10 days. For rapid strength concrete may be at 4 days.
Vinod kumar kesari said:
1 decade ago
Dear Sir,
I am bit confused at which concept you have to take deshuttering made for slab within 4 days. Setting of concreting depend on environmental condition, span and thickness. But how it would be for 4 days only please explain.
I am bit confused at which concept you have to take deshuttering made for slab within 4 days. Setting of concreting depend on environmental condition, span and thickness. But how it would be for 4 days only please explain.