Discussion Forum : Building Construction - Section 4 (Q.No. 4)
4.
The form work from the slabs excluding props, can be removed only after
Discussion:
17 comments Page 2 of 2.
Krishan murari roy said:
10 years ago
Shuttering removing after 7 days under 4.5 meter in span.
RANJIT CHAUHAN said:
8 years ago
That no specifiy soffit slab the correct answer is 7.
Ashish Tadewar said:
8 years ago
4 days? How? Can anyone explain it clearly?
Roy said:
8 years ago
3 days should be the correct answer.
Mahesh sinh said:
8 years ago
I think as per IS 456 it's 7 days.
Akshay said:
6 years ago
What is the meaning of props?
(1)
Ahmed said:
8 years ago
14 days required is correct.