Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
| If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
| 2 |
So, A takes 30 days to do the work.
| A's 1 day's work = | 1 |
| 30 |
| B's 1 day's work = | 1 |
| 90 |
| (A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
| 30 | 90 | 90 | 45 |
A and B together can do the work in |
45 | = 22 | 1 | days. |
| 2 | 2 |
Discussion:
284 comments Page 14 of 29.
Nagarjun said:
2 decades ago
@Vikas
Its just cross multiplication.
If the difference is 2 days then b takes 3 days
If the difference is 60 days then b takes x days
Hence, x= (60*3)/2.
I think you got it now.
Its just cross multiplication.
If the difference is 2 days then b takes 3 days
If the difference is 60 days then b takes x days
Hence, x= (60*3)/2.
I think you got it now.
Pramod nepal said:
8 years ago
Let see @Shaman.
A finish work in x day and B can 5x day. Then we can do A+B= 1/x +1/5x.
We have A+B = 50,
50 = 5x/6 after sol x= 60 it means A can do in 60 min and B 300 min.
A finish work in x day and B can 5x day. Then we can do A+B= 1/x +1/5x.
We have A+B = 50,
50 = 5x/6 after sol x= 60 it means A can do in 60 min and B 300 min.
Suresh said:
9 years ago
A is 3 times more efficient than B,
A=3B
A do the work less than 60 days compared to B,
A-60=B.
So, we can write it as,
A = 3(A+60)
A = 3A+180
2A = 180
A = 90
90-60 = B
B = 30.
A=3B
A do the work less than 60 days compared to B,
A-60=B.
So, we can write it as,
A = 3(A+60)
A = 3A+180
2A = 180
A = 90
90-60 = B
B = 30.
Taukir said:
1 year ago
A takes time = x days.
So, B takes time = 3x days
Now, 3x - x = 60 days
X = 30
3x = 90
1/30 + 1/90 = 1/20 (working together in 1 day).
So, They can do the whole work in 20 days.
So, B takes time = 3x days
Now, 3x - x = 60 days
X = 30
3x = 90
1/30 + 1/90 = 1/20 (working together in 1 day).
So, They can do the whole work in 20 days.
(87)
Harsha said:
2 years ago
A takes x-60 days.
B takes x days.
If A does work in 1 day then B takes 3 days.
So,
1/(x-60) = 1/x
Solving this we get x = 90
Now, A+B can do work in 1/90 + 3/90.
We get 45/2.
B takes x days.
If A does work in 1 day then B takes 3 days.
So,
1/(x-60) = 1/x
Solving this we get x = 90
Now, A+B can do work in 1/90 + 3/90.
We get 45/2.
(49)
M ahmad said:
1 decade ago
A can do the job in x days.
B can same job in 3x days.
3x=x+60 by B.
x=30.
One day work by A and B = 1/30+1/90 = 4/90 = 2/45.
Whole job done by A and B = 45/2 = 22.5 days.
B can same job in 3x days.
3x=x+60 by B.
x=30.
One day work by A and B = 1/30+1/90 = 4/90 = 2/45.
Whole job done by A and B = 45/2 = 22.5 days.
Sahil Husain said:
9 years ago
A=3B ----------(1)
A-60=B----------(2) from equation 1 & 2
3B-60 = B
B=30 and A = 90
(A+B)'S 1 day work =1\90+1\30 = 2\45,
So (A+B)'s work = 45\2 = 22 1\2.
A-60=B----------(2) from equation 1 & 2
3B-60 = B
B=30 and A = 90
(A+B)'S 1 day work =1\90+1\30 = 2\45,
So (A+B)'s work = 45\2 = 22 1\2.
Aya adel said:
2 years ago
a : b
1 : 3.
And x-60:x
Then 3(x - 60) = x.
3x-180 = x,
2x = 180,
x = 90.
a = 90 - 60 = 30
b = 90
1\a + 1\b = 1\30 + 1\90 = 2\45.
a + b = 45\2.
So, the answer is 22 1\2.
1 : 3.
And x-60:x
Then 3(x - 60) = x.
3x-180 = x,
2x = 180,
x = 90.
a = 90 - 60 = 30
b = 90
1\a + 1\b = 1\30 + 1\90 = 2\45.
a + b = 45\2.
So, the answer is 22 1\2.
(57)
HARINI said:
4 years ago
Given;
A = 3B;
A = B - 60.
Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.
Therefore; A = 3B = 90.
A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
A = 3B;
A = B - 60.
Substitute A = 3B in 2nd equation(a=b-60).
3B = B-60
B = 30.
Therefore; A = 3B = 90.
A+B = (1/30 + 1/90) = 2/45.
So, the answer is 22(1/2).
(24)
Tiya said:
8 years ago
Please solve this question.
If the ratio of work efficiency of A and B is 3:2. If A and B together finish a work in 5 days in how much days B alone complete the work?
If the ratio of work efficiency of A and B is 3:2. If A and B together finish a work in 5 days in how much days B alone complete the work?