Aptitude - Time and Work - Discussion
Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
Answer: Option
Explanation:
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes | ![]() |
3 | x 60 | ![]() |
= 90 days. |
2 |
So, A takes 30 days to do the work.
A's 1 day's work = | 1 |
30 |
B's 1 day's work = | 1 |
90 |
(A + B)'s 1 day's work = | ![]() |
1 | + | 1 | ![]() |
= | 4 | = | 2 |
30 | 90 | 90 | 45 |
![]() |
45 | = 22 | 1 | days. |
2 | 2 |
Discussion:
281 comments Page 11 of 29.
Anji said:
1 decade ago
Let the time taken by A be x days,
then time taken by B will be 3x days.
Given that,
time taken by A to finish the work = time taken by B -60
i.e, x=3x-60
=> x=30.
Therefore, time taken by A to finish the work is 30 days.
so B takes 90 days.
Now ,work done by A & B in 1 day=1/30 + 1/90
=4/90
=2/45
Time taken by A & B to complete the work=45/2 days
=22 1/2 days
then time taken by B will be 3x days.
Given that,
time taken by A to finish the work = time taken by B -60
i.e, x=3x-60
=> x=30.
Therefore, time taken by A to finish the work is 30 days.
so B takes 90 days.
Now ,work done by A & B in 1 day=1/30 + 1/90
=4/90
=2/45
Time taken by A & B to complete the work=45/2 days
=22 1/2 days
SANJEEV said:
1 decade ago
#include<stdio.h>
void main()
{
float a,b;
int c,d;
printf("enter ratio of A : B\n");
scanf("%f",&a);
printf("enter no of days lesser than B by A to complete work\n");
scanf("%f",&b);
c=ab/(a-1);
d=c-b;
printf("no of days to complete work by A and B is %d",(c*d)/(c+d));
}
void main()
{
float a,b;
int c,d;
printf("enter ratio of A : B\n");
scanf("%f",&a);
printf("enter no of days lesser than B by A to complete work\n");
scanf("%f",&b);
c=ab/(a-1);
d=c-b;
printf("no of days to complete work by A and B is %d",(c*d)/(c+d));
}
Prabha said:
1 decade ago
If difference of time 2 days B takes 3 days
Similarly why don't we take difference of time 60 days B takes 60*3 is 180 days. Please explain to me ?
Similarly why don't we take difference of time 60 days B takes 60*3 is 180 days. Please explain to me ?
Joshi Sir said:
1 decade ago
Friends, don't make it complex: Here we go.
Ratio of time taken by A & B = 1:3
And A takes 60 days less then B
Suppose, days taken by B = x then days taken by A = (x - 60)
Thus,
A : B = (x - 60) : x
1 : 3 = (x - 60) : x
1/3 = (x - 60) / x
X = 3 (x - 60)
X = 3x - 180
180 = 3x - x
180 = 2x
X = 180 / 2 = 90
Hence,
Days taken by B = x = 90 days
Days taken by A = (x - 60) = 90 - 60 = 30 days
1 day work of A and B = 1/30 + 1/90
= 4/90
= 2/45
So,
Total days taken by A & B to complete the work = 45/2 = 22.5 days
Ratio of time taken by A & B = 1:3
And A takes 60 days less then B
Suppose, days taken by B = x then days taken by A = (x - 60)
Thus,
A : B = (x - 60) : x
1 : 3 = (x - 60) : x
1/3 = (x - 60) / x
X = 3 (x - 60)
X = 3x - 180
180 = 3x - x
180 = 2x
X = 180 / 2 = 90
Hence,
Days taken by B = x = 90 days
Days taken by A = (x - 60) = 90 - 60 = 30 days
1 day work of A and B = 1/30 + 1/90
= 4/90
= 2/45
So,
Total days taken by A & B to complete the work = 45/2 = 22.5 days
Ashutosh said:
1 decade ago
Formula-->nx- (n+1) /nx.
4x-4x/3=60 so x=45/2.
4x-4x/3=60 so x=45/2.
Keerthi said:
1 decade ago
So by the explanation above we have to take in the ratio 1:3.
Kavya said:
1 decade ago
A is twice as good a workmen as B and together they can finish a piece of work in 18days. In how many days will A alone finish the work?
Can we solve the above problem using the formula k*x/k^2-1.
Can we solve the above problem using the formula k*x/k^2-1.
Pankaj said:
1 decade ago
Let A takes x days to do the work alone
Therefore days taken by b is (x+60).
Now A is 3 times faster than B
So no.of days taken by A will be 3 times less than B.
So
3*x=(x+60)
2x=60
x=30 days //work done by A
Work done by B=30+60=90 days.
Now we can find work done together
1/30 +1/90 to get the answer.
Therefore days taken by b is (x+60).
Now A is 3 times faster than B
So no.of days taken by A will be 3 times less than B.
So
3*x=(x+60)
2x=60
x=30 days //work done by A
Work done by B=30+60=90 days.
Now we can find work done together
1/30 +1/90 to get the answer.
Monika said:
1 decade ago
We have a direct formula for these kind of questions .. i.e.,
Work done together is given by = (m*d)/(m^2 - 1),
Where d is no of days taken by B and m is no of time A is faster than B,
Therefore = (3*60)/(3^2-1) = 22.5.
Work done together is given by = (m*d)/(m^2 - 1),
Where d is no of days taken by B and m is no of time A is faster than B,
Therefore = (3*60)/(3^2-1) = 22.5.
Praveen said:
1 decade ago
@All.
Please refer to Sheetal's response as given below. Its the best and easiest way to solve such questions.
PS:Thanks sheetal.
"A is K times as good a worker as B & takes X days less than B to finish the work. Then the amount of time required by A & B working together is K * X / K'S SQUARE - 1.
SO IN QUESTION K IS 3. X IS 60. SO PUTTING THE VALUES IN ABOVE MENTIONED FORMULA.
K * X / K'S SQUARE - 1
=3 * 60 / 9 - 1
=3 * 60 / 8
=180 / 8
=22.5 DAYS.
AS MENTIONED OPTION B.
Please refer to Sheetal's response as given below. Its the best and easiest way to solve such questions.
PS:Thanks sheetal.
"A is K times as good a worker as B & takes X days less than B to finish the work. Then the amount of time required by A & B working together is K * X / K'S SQUARE - 1.
SO IN QUESTION K IS 3. X IS 60. SO PUTTING THE VALUES IN ABOVE MENTIONED FORMULA.
K * X / K'S SQUARE - 1
=3 * 60 / 9 - 1
=3 * 60 / 8
=180 / 8
=22.5 DAYS.
AS MENTIONED OPTION B.
Post your comments here:
Quick links
Quantitative Aptitude
Verbal (English)
Reasoning
Programming
Interview
Placement Papers