Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
281 comments Page 11 of 29.

Deepak Patgar said:   1 decade ago
Let A completes work in x days.
So no of days taken by B to complete the same work will be 3x days.

A takes 60 days less than B.

So 3x-60 = x.
2x = 60.
x = 30 days (number of days taken by A).
3x = 90 days (number of days taken by B).

Work done by A per day is 1/30.
Work done by B per day is 1/90.

Work done the together in 1 day will be (1/30+1/90) = 4/90.

So work done by them in 10 days will be 40/90.

Work done in 20 days 80/90.

Number of days require to do the remaining 10/90 will be 2.5 days.

Ans = 22.5 days.

Poor gamer said:   1 decade ago
Let A takes x days and B takes 60+x days.
Its given that A takes 1 days when B takes 3 days.

So,
1/3 = x/x+60.

Cross multiply and we get x = 30 i.e A.
X+60 = 30 + 60 = 90 i.e B.

Remaining as usual.

Divyanshu Dwivedi said:   1 decade ago
Simple:

A's work = x.
B's work = y = 3x.

Hence acc. to ques.: 3x - x = 60 ;.
x=30 A's.
y=90 B's.

Now.... 1/30 + 1/90 = 1/z.

z = 90/4 Answer.

Mohit jain said:   1 decade ago
Let,

A takes = x days.
B will take = 3x days.

Difference 3x-x = 60.

So 2x = 60.
x = 30 days.

Thus A can do it in 30 days and B in 90 days.

Sumit said:   1 decade ago
If difference of time is 60 days, B takes 3/2 x 60 = 90 days.

Please explain this statement.

Prakash said:   1 decade ago
But there is not given difference in question they given A finish work in 60 day?

Ankita said:   1 decade ago
If B takes y days , A takes (y-60 ) days. Now , their efficiency are A:B = 3x : x.

So total unit of work is 3x*(y- 60 ) man days = x*y man days.

Calculating this we get y = 90. So if B worked for 90 days, A worked for 30 days.

Hence 1/30 + 1/90 = 22 1/2 days :).

Priya said:   1 decade ago
No need to do all that simply guess numbers 30 & 90 which is satisfying this then without using pen we can get answer 22.5 days.

Ankita said:   1 decade ago
Suppose A takes x days.

Then, B will take 3x days.

From question, 3x-x = 60.

=> x = 30.

=> A takes 30 days and B takes 90 days.

Together they will take = 30*90/30+90.

= 30*90/120.

= 90/4.

= 22.5 or 22 1/2 days (ans).