Aptitude - Time and Work - Discussion

Discussion Forum : Time and Work - General Questions (Q.No. 4)
4.
A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22 1 days
2
25 days
30 days
Answer: Option
Explanation:

Ratio of times taken by A and B = 1 : 3.

The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.

If difference of time is 2 days, B takes 3 days.

If difference of time is 60 days, B takes 3 x 60 = 90 days.
2

So, A takes 30 days to do the work.

A's 1 day's work = 1
30

B's 1 day's work = 1
90

(A + B)'s 1 day's work = 1 + 1 = 4 = 2
30 90 90 45

A and B together can do the work in 45 = 22 1 days.
2 2

Discussion:
283 comments Page 1 of 29.

Lalith kumar said:   1 month ago
First, A is thrice as good as B means.

If a takes a day to complete work, then b takes 3 days to complete the same work.

Here, time is inversely proportional to work.

So if b takes time T to complete, then a takes T/3 to complete.
In question, they mentioned that the time diff is 60 days.
So, T - T/3 = 60.
2T/3 = 60.
T = 90.
Now, calculate the combined work and how many days it will take.
1/30 + 1/90 = 2/45 = 22.5.
(2)

Mishra said:   1 month ago
Given: A takes 60 days less than B.
So, let A takes 90days,
B takes 30days.

LCM of 90, 30 = 180 and effeciency of A = 2 (180/90), B = 6 (180/30);
Both work together A + B = (2+6) = 8;
So, total work = 180(LCM);
total days = work/efficiency of both.
= 180/8 = 22.5.
(6)

Yash Sangle said:   3 months ago
3/1 = (B)/(B-60).
As work done and time are inversely related,
so, B = 90, A = 30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
(9)

Yash Sangle said:   3 months ago
3/1 = (B)/(B-60).

As work done and time are inversely related,
So, B=90, A=30.
(1/90 + 1/30) = (2/45),
So, 22 1/5.
(2)

Nallapu Rishith Reddy said:   3 months ago
3/1 = (B)/(B-60).
As work done and time are inversely related,
so, B=90, A=30.
(1/90+1/30)=(2/45),
So, 22 1/5.
(5)

Raseswari said:   5 months ago
I am not understanding this question.

Anyone help me to get it be explaining it along with the formulas?
(17)

Nikita raisadhar said:   7 months ago
3x - x=60
2x = 60
x = 30
B = 3x = 3 x 30 = 90.
A+B = 1/30 + 1/90,
= 3 + 1/90,
= 4/90,
= 2/42,
= 45/2,
= 22 1/2.
(54)

Subhranil Mondal said:   7 months ago
Assume B can do it in x days.
So A can in x/3 days.
x - x/3 = 60.
then x = 90.
So B can do the work in 90 days.
A can do it in 90/3 = 30 days.
A and B together can do it in 90 * 30/90 + 30 = 22.5 (Ans).
(22)

Taukir said:   11 months ago
A takes time = x days.
So, B takes time = 3x days
Now, 3x - x = 60 days
X = 30
3x = 90
1/30 + 1/90 = 1/20 (working together in 1 day).
So, They can do the whole work in 20 days.
(85)

Furquan Shiekh said:   1 year ago
Suppose A takes x days to complete the work.
Therefore, B will take 3x days.
Now, x = 3x- 60.
x= 30 days.

Thus A takes 30 days and B takes 90 days.
Therefore work done by both in 1 day will be (1/30 + 1/90) = 4/90.

Therefore they take (90/4) = 22.5 days to complete the work.
(75)


Post your comments here:

Your comments will be displayed after verification.