In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 3 of 4.
Anomy said:
9 years ago
Critical path.
The sequence of stages determining the minimum time needed for an operation, especially when analyzed on a computer for a large organization.
The sequence of stages determining the minimum time needed for an operation, especially when analyzed on a computer for a large organization.
Bhavesh Shingala said:
9 years ago
Critical path does not contain dummy activities. So B is incorrect.
AMAL said:
10 years ago
Option [B] is the correct answer. The dummy activities are provided to show precedence before any activity. Here it is showing that after 3 we can go to point 5.
And the critical path is the one taking the longest time in cycle. There is nothing like we cannot consider dummy in critical path. 1-2-3-5-6-7-8-9 is taking 24 units that's why it will be critical path.
And the critical path is the one taking the longest time in cycle. There is nothing like we cannot consider dummy in critical path. 1-2-3-5-6-7-8-9 is taking 24 units that's why it will be critical path.
Janardhan reddy.G said:
10 years ago
1-2-3-4-8-9 = 21.
1-2-3-5-6-7-8-9 = 24.
1-2-5-6-7-8-9 = 22.
By comparing the critical path from the above, it is concluded that option B is correct. That is critical path is given by 1-2-3-5-6-7-8-9.
Whenever if we want to know the critical path we need to consider dummy activities also for the completion of project.
1-2-3-5-6-7-8-9 = 24.
1-2-5-6-7-8-9 = 22.
By comparing the critical path from the above, it is concluded that option B is correct. That is critical path is given by 1-2-3-5-6-7-8-9.
Whenever if we want to know the critical path we need to consider dummy activities also for the completion of project.
Rash Bihari said:
10 years ago
Dummy activity should be considered. So option B is correct.
Chirag Arya said:
1 decade ago
Dummy activity not considered so D is correct. It takes 22 days.
Jimbru said:
1 decade ago
Dummy activity will also be considered.
Vinit said:
1 decade ago
Critical path does not contain dummy activities. So B is incorrect.
Jay shankar bhatt said:
1 decade ago
Option B is not correct because we avoid looping in critical path.
Abhishek said:
1 decade ago
Option B is 100% correct because it highest 24 days to complete a project and their are no effect of dummy activity for critical path.
Post your comments here: