Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 15)
15.
In a network shown in the below figure, the critical path is along


Discussion:
32 comments Page 2 of 4.
Vetan said:
6 years ago
The critical path has the longest path and consumes maximum time and maximum resource
So option B is correct.
1-2-3-5-6-7-8-9 = 24.
So option B is correct.
1-2-3-5-6-7-8-9 = 24.
Bhargav said:
6 years ago
According to me, Option A is the correct answer.
Dhaval Chaudhary said:
6 years ago
A is correct answer 1-2-3-4-8-9.
Ref: R S Kurmi.
Ref: R S Kurmi.
Anand said:
7 years ago
CRITICAL Path:
A critical path consumes maximum resources. It is the longest path and consumes maximum time.
So the order of the network is 1-2-3-5-6-7-8-9.
Option B is correct.
A critical path consumes maximum resources. It is the longest path and consumes maximum time.
So the order of the network is 1-2-3-5-6-7-8-9.
Option B is correct.
Samuel said:
7 years ago
Exactly @Neeraj. But according to the definition, critical path is the longest path and consumes maximum time. So, they are contradicting each other.
Neeraj said:
7 years ago
I think it is A.
Ref: RS Khurmi.
Ref: RS Khurmi.
Kuldip said:
1 decade ago
Critical path is one which takes more time to complete. So 1-2-5-6-7-8-9 is taking 22 days and other path 21 day so 1256789 should be the critical path.
Manoj said:
8 years ago
Which takes minimum time? Explain in detail.
ONOSETALE said:
8 years ago
@ALL.
As an Industrial engineer, one of the function in a project is to obtain an optimal solution. However, I would suggest those against option B to study the algorithm of network diagram as regarding selecting the critical path(s).
As an Industrial engineer, one of the function in a project is to obtain an optimal solution. However, I would suggest those against option B to study the algorithm of network diagram as regarding selecting the critical path(s).
Ind Lov said:
9 years ago
The Crictical path can contain Dummy activities.
So answer B is right.
So answer B is right.