Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 41)
41.
When slack of an activity is positive
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
23 comments Page 3 of 3.

Shivaprasad said:   6 years ago
The Correct answer is A.

Tinku said:   7 years ago
Option A is correct.

Manoj said:   8 years ago
I agree @Ashu.


Post your comments here:

Your comments will be displayed after verification.