41. 

When slack of an activity is positive

A. it represents a situation where extra resources are available and the completion of project is not delayed
B. it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C. the activity is critical and any delay in its performance will delay the completion of whole project
D. any one of the above

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

42. 

For a small scale industry, the fixed cost per month is Rs. 5000. The variable cost per product is Rs. 20 and sales price is Rs. 30 per piece. The break even production per month will be

A. 300
B. 460
C. 500
D. 1000

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

43. 

Follow-up prescribes the sequence of operations to be followed.

A. Correct
B. Incorrect

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.

44. 

Dummy activities are used to

A. determine the critical path
B. determine the project completion time
C. maintain the required net work
D. none of these

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

45. 

Which of the following statement is wrong?

A. An activity consume time and resources whereas an event do not consume time or resources.
B. The performance of a specific task is called an activity.
C. An event is an instantaneous point in time at which an activity begins or ends.
D. The turning of a job on lathe is an event whereas job turned is an activity.

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.