Mechanical Engineering - Industrial Engineering and Production Management

Exercise : Industrial Engineering and Production Management - Section 2
1.
A critical activity has
maximum slack
minimum slack
zero slack
average slack
Answer: Option
Explanation:
No answer description is available. Let's discuss.

2.
Sampling method of determining standard time is profitable for long cycle operation.
Correct
Incorrect
Answer: Option
Explanation:
No answer description is available. Let's discuss.

3.
Break even analysis is a
short term analysis
long term analysis
average of short and long term analysis
any one of these
Answer: Option
Explanation:
No answer description is available. Let's discuss.

4.
In a functional organisation
quality of work is better
wastage of material is minimum
specialised knowledge and guidance to individual worker is provided
all of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.

5.
The purpose of micromotion study is to
assist in finding out the most efficient way of doing work
train the individual operator regarding the motion economy principles
help in collecting the motion time data for synthetic time standards
all of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.