Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 41)
41.
When slack of an activity is positive
it represents a situation where extra resources are available and the completion of project is not delayed
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
the activity is critical and any delay in its performance will delay the completion of whole project
any one of the above
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
23 comments Page 2 of 3.

Kuldip said:   7 years ago
According to me, A is the correct answer.

Nitesh said:   6 years ago
According to me, the right answer is A.

Himanshu said:   7 years ago
According to me, Option A is right.

Jainesh said:   7 years ago
Correct answer is (a). I too agree.

Bhavesh Shingala said:   8 years ago
The correct answer is - option [A].

A.Abhilash said:   6 years ago
Option A is the correct answer.

Subodh Kumar said:   5 years ago
Yes, Option A is correct.

Vaiovino said:   7 years ago
The Correct option is A.

Gopal said:   7 years ago
A is the correct answer.

Vipul kumar said:   7 years ago
A is the correct answer.


Post your comments here:

Your comments will be displayed after verification.