Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 41)
                   
                                       
                                41.
When slack of an activity is positive
 
                                    Discussion:
23 comments Page 3 of 3.
                
                        Kamal Bansal said: 
                         
                        1 decade ago
                
                Slack or float is time by which any activity delay without delaying project completion.
Positive slack-----Ahead of schedule.
Negative slack------Behind the schedule.
Zero slack ---------On the schedule.
                Positive slack-----Ahead of schedule.
Negative slack------Behind the schedule.
Zero slack ---------On the schedule.
                        Navin said: 
                         
                        1 decade ago
                
                When slack is zero at that time activity is critical. So correct is "A".
                
                        Alpesh said: 
                         
                        1 decade ago
                
                When slack of an activity is positive means slack may be zero and higher. For this reason option C shall be also true. So that option D is correct.