Discussion Forum : Industrial Engineering and Production Management - Section 2 (Q.No. 41)
                   
                                       
                                41.
When slack of an activity is positive
 
                                    Discussion:
23 comments Page 2 of 3.
                
                        Vaiovino said: 
                         
                        8 years ago
                
                The Correct option is A.
                
                        Gopal said: 
                         
                        8 years ago
                
                A is the correct answer.
                
                        Daya said: 
                         
                        1 decade ago
                
                When slack of an activity is positive - the correct answer is - option [A]. It represents a situation where extra resources are available and the completion of project is not delayed.
                
                        Ganeswar said: 
                         
                        8 years ago
                
                The Answer should be A because positive does not include zero. Hence extra resource is available and the project is ahead of schedule.
                
                        Chotu said: 
                         
                        8 years ago
                
                Answer A is correct.
Because positive slack never be behind the schedule or on the critical path.
                Because positive slack never be behind the schedule or on the critical path.
                        Samod said: 
                         
                        8 years ago
                
                I too think the Correct answer is option A.
                
                        Jainesh said: 
                         
                        9 years ago
                
                Correct answer is (a). I too agree.
                
                        Manoj said: 
                         
                        9 years ago
                
                I agree @Ashu.
                
                        Ashu panchal said: 
                         
                        9 years ago
                
                The correct answer is option [A].
When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.
When slack of an activity is negative- it represents that a program falls behind schedule and additional resources are required to complete the project in time.
When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.
                When slack of an activity is positive - it represents a situation where extra resources are available and the completion of the project is not delayed.
When slack of an activity is negative- it represents that a program falls behind schedule and additional resources are required to complete the project in time.
When slack of an activity is zero - the activity is critical and any delay in its performance will delay the completion of the whole project.
                        Bhavesh Shingala said: 
                         
                        9 years ago
                
                The correct answer is - option [A].
                Post your comments here:
 
            