Yeskig said:
6 years ago
Performance Rating.
During the time study, time study engineer carefully observes the performance of the operator. This performance seldom conforms to the exact definition of normal or standard. Therefore, it becomes necessary to apply some 'adjustment' to the mean observed time to arrive at the time that the normal operator would have taken to do that job when working at an average pace. This 'adjustment' is called Performance Rating.
Determination of performance rating is an important step in the work measurement procedure. It is based entirely on the experience, training, and judgment of the work-study engineer. It is the step most subjective and therefore is subject to criticism.
Performance Rating can be defined as the procedure in which the time study engineer compares the performance of operator (s) under observation to the Normal Performance and determines a factor called Rating Factor.
During the time study, time study engineer carefully observes the performance of the operator. This performance seldom conforms to the exact definition of normal or standard. Therefore, it becomes necessary to apply some 'adjustment' to the mean observed time to arrive at the time that the normal operator would have taken to do that job when working at an average pace. This 'adjustment' is called Performance Rating.
Determination of performance rating is an important step in the work measurement procedure. It is based entirely on the experience, training, and judgment of the work-study engineer. It is the step most subjective and therefore is subject to criticism.
Performance Rating can be defined as the procedure in which the time study engineer compares the performance of operator (s) under observation to the Normal Performance and determines a factor called Rating Factor.
Lucky said:
9 years ago
Performance Rating can be defined as the procedure in which the time study engineer compares the performance of operator (s) under observation to the Normal Performance and determines a factor called Rating Factor. There are several systems of rating the performance of operator on a job.
So, option "D" is perfect.
So, option "D" is perfect.
Arjun said:
1 decade ago
Rating factor is the process during which the time study analyst compares the performance (speed) of the operator observed with the observer's (analyst) own concept of normal performance.
This rating factor is then applied to the observed time to obtain the normal time for the job.
Answer is "D".
This rating factor is then applied to the observed time to obtain the normal time for the job.
Answer is "D".
Sidharth Jain said:
1 decade ago
Rating factor is used for determining normal time, which can be further used to determine standard time, which then is used to fix up the incentives in accordance with the performance of person, so no single option can be chosen.
Raj Kumar Singh said:
9 years ago
Answer is D. Since the rating is assessment work rate o f working relative to the observer.
Normal time = observed time x rating. So it is used to define Normal time.
Normal time = observed time x rating. So it is used to define Normal time.
(1)
Arvind said:
8 years ago
Since rating factor is used to determine standard time and standard time is used to determine fixation of incentive rate " ultimately so (c) is the correct answer.
Arunmishra said:
1 decade ago
Rating factor is used to determine the normal time. And after adding allowances on normal time we can calculate the standard time. So answer is D.
Ashu said:
8 years ago
It not asking about the rating factor it is asking why it is applied what is the outcome after applying so in my view, option C is correct.
Ravi said:
1 decade ago
@Arjun is right rating factor used to determine the normal time. It is applicable only for human worker.
Rahul said:
1 decade ago
Rating factor is use to determine normal time only. It is applied for worker only not for machine.