Mechanical Engineering - Industrial Engineering and Production Management - Discussion
Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 2)
2.
In time study, the rating factor is applied to determine
Discussion:
28 comments Page 2 of 3.
BSp said:
1 decade ago
Yes @Arjun is right.
Normal time = observed time * rating factor.
Normal time = observed time * rating factor.
Samuel said:
7 years ago
The answer is a fixation of incentive rate.
Ref: S.Chand.
Ref: S.Chand.
SANJAY said:
9 years ago
Then, what is mean by fixation of incentive rate?
Sai said:
9 years ago
I think answer is the normal time of a work.
Jaysukh Viramgami said:
4 years ago
Correct Answer is C.
Referance R.S Khurmi.
Referance R.S Khurmi.
(1)
Shivaprasad said:
7 years ago
C is the correct answer.
Ref: R S Khurmi.
Ref: R S Khurmi.
SK CHOUDHARY said:
4 years ago
C is the correct answer.
Ref; RS Khurmi.
Ref; RS Khurmi.
(3)
Rafi said:
8 years ago
Answer c is the correct agree@Aravind.
Chetan Tadkal said:
8 years ago
C is correct as per R K Kurmi book.
Raviteja said:
1 decade ago
It depends on time and the worker.
Post your comments here: