Mechanical Engineering - Industrial Engineering and Production Management

Exercise : Industrial Engineering and Production Management - Section 3
26.
An activity of the project is graphically represented by __________ on the network diagram.
a circle
a straight line
an arrow
Answer: Option
Explanation:
No answer description is available. Let's discuss.

27.
According to Rowan plan of wage incentive system, bonus is paid to a worker
whose output exceeds 67% efficiency
on the percentage of time saved
on the percentage of time worked
on the percentage of standard time
Answer: Option
Explanation:
No answer description is available. Let's discuss.

28.
Which of the following charts are used for plant layout design?
Operation process chart
Man machine chart
Travel chart
all of these
Answer: Option
Explanation:
No answer description is available. Let's discuss.

29.
Earliest finish time can be regarded as
earliest start time + duration of activity
earliest start time - duration of activity
latest finish time + duration of activity
latest finish time - duration of activity
Answer: Option
Explanation:
No answer description is available. Let's discuss.

30.
If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be
TR
TR + (S - T)R
Answer: Option
Explanation:
No answer description is available. Let's discuss.