Discussion Forum : Industrial Engineering and Production Management - Section 3 (Q.No. 29)
29.
Earliest finish time can be regarded as
earliest start time + duration of activity
earliest start time - duration of activity
latest finish time + duration of activity
latest finish time - duration of activity
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
1 comments Page 1 of 1.

Rajkotha said:   4 years ago
Duration of activity = earliest finish time -earliest start time.