Mechanical Engineering - Industrial Engineering and Production Management

Exercise : Industrial Engineering and Production Management - Section 1
16.
Bar chart is suitable for
large project
major work
minor work
all of these
Answer: Option
Explanation:
No answer description is available. Let's discuss.

17.
Which one of the following chart gives simultaneously information about the progress of work and machine loading?
Process chart
Machine load chart
Man-machine chart
Gantt chart
Answer: Option
Explanation:
No answer description is available. Let's discuss.

18.
Probabilistic time for completion of any activity can be found out from
optimistic time
pessimistic time
most likely time
all of these
Answer: Option
Explanation:
No answer description is available. Let's discuss.

19.
Line organisation is suitable for a big organisation.
Correct
Incorrect
Answer: Option
Explanation:
No answer description is available. Let's discuss.

20.
PERT is an event oriented technique.
Correct
Incorrect
Answer: Option
Explanation:
No answer description is available. Let's discuss.