16. 

Bar chart is suitable for

A. large project
B. major work
C. minor work
D. all of these

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

17. 

Which one of the following chart gives simultaneously information about the progress of work and machine loading?

A. Process chart
B. Machine load chart
C. Man-machine chart
D. Gantt chart

Answer: Option C

Explanation:

No answer description available for this question. Let us discuss.

18. 

Probabilistic time for completion of any activity can be found out from

A. optimistic time
B. pessimistic time
C. most likely time
D. all of these

Answer: Option D

Explanation:

No answer description available for this question. Let us discuss.

19. 

Line organisation is suitable for a big organisation.

A. Correct
B. Incorrect

Answer: Option B

Explanation:

No answer description available for this question. Let us discuss.

20. 

PERT is an event oriented technique.

A. Correct
B. Incorrect

Answer: Option A

Explanation:

No answer description available for this question. Let us discuss.