Mechanical Engineering - Industrial Engineering and Production Management - Discussion

Discussion Forum : Industrial Engineering and Production Management - Section 1 (Q.No. 17)
17.
Which one of the following chart gives simultaneously information about the progress of work and machine loading?
Process chart
Machine load chart
Man-machine chart
Gantt chart
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
7 comments Page 1 of 1.

Chatgpt said:   12 months ago
The chart that simultaneously provides information about the progress of work and machine loading is the "Machine load chart. "

This type of chart displays the utilization or loading of machines over time, showing when they are idle, in use, or overloaded. It allows you to assess the efficiency of machine usage and identify potential bottlenecks in production. So, the correct answer is "Machine load chart".

Gurudas Goswami said:   2 years ago
Man-machine chart:
A Man-machine chart graphically represents the relationship between the manual work performed by one or more operators and one or more machines involved in a manufacturing process.

Bar Chart:
The bar chart (Gantt chart) is used for the representation of a project in which horizontal bars represent activities, length of each bar is proportional to the time necessary to complete the task.

Pie Chart:
It is a type of graph that shows data in a circular shape which is further divided into different sectors for representing the data of that particular part out of the whole part.

Machine load chart:
It is a schematic and graphic way to represent the amount of authorized work yet to be performed by a machine or any other producing unit in a factory.

This chart will also indicate the capacity over both ends and sides of the machine.

Ram said:   6 years ago
But according to Kurmi it is C.

So, I agree with the given answer.

R A Bahadur said:   7 years ago
I think B is correct.

Yuvi said:   8 years ago
I think it is Gantt chart.

Vinit said:   8 years ago
Yes, the correct answer is B.

Sambhu jana said:   8 years ago
I think it is process chart.

Post your comments here: