17.
The expected out turn of half brick partition wall per mason per day is
1.5 m3
2.0 m3
4.0 m2
5.0 m2
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
50 comments Page 5 of 5.

Yadav said:   4 years ago
Substructure 1.25m3.
Superstructure 1.00m3.
Mud mortar - 1.5 and 1.25 m3.
Arches .55 m3.
Half brick 5 m2.
RCC 3 m3.
RB 1 m3.
12mm plastering 8 m2.
(1)

Aman said:   4 years ago
5m2 is the correct answer.

Jagat Khadka said:   3 years ago
5m^2 is the Correct Answer.

Engr khan said:   3 years ago
Option D. 5 m^2 is the correct answer.
(1)

Narendra said:   3 years ago
Half brick work is in sq.m.

Dr. Buch said:   3 years ago
Substructure: 1.25m3.
Superstructure: 1.00m3.
Mud mortar: 1.5 and 1.25 m3.
Arches: 55 m3.
Half brick: 5 m2.
RCC: 3 m3.
RB: 1 m3.
12mm plastering 8 m2.
(2)

Alpesh mali said:   3 years ago
D is right.

Substructure: 1.25m^3.
Superstructure: 1.00m^3.
Mud mortar: 1.5 and 1.25 m^3.
Arches: 55 m^3.
Half brick: 5 m^2.
(1)

James said:   2 years ago
I think the correct answer, is option (d).

Uttam Khanra said:   2 years ago
First, Half bricks partition wall will be in m2. It will be 7.5m2.

Bashishth Baitha said:   2 years ago
I think the correct answer is option D.