Civil Engineering - Estimating and Costing
Exercise :: Estimating and Costing - Section 1
36. |
The area is measured correct to the nearest |
A. |
0.01 sqm | B. |
0.02 sqm | C. |
0.03 sqm | D. |
0.04 sqm | E. |
0.05 sqm |
Answer: Option A
Explanation:
|
37. |
Cost of fittings and their fixing is specified for the following sanitary fittings |
A. |
Water closets | B. |
Flushing pipes | C. |
Lavatary basins | D. |
Sinks | E. |
All the above. |
Answer: Option E
Explanation:
|
38. |
The volume is measured correct to the nearest |
A. |
0.01 cum | B. |
0.02 cum | C. |
0.03 cum | D. |
0.04 cum | E. |
0.05 sum |
Answer: Option A
Explanation:
|
39. |
Pick up the correct statement from the following: |
A. |
The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men | B. |
The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work | C. |
The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids | D. |
All the above. |
Answer: Option D
Explanation:
|
40. |
Pick up the item whose weight is added to the weight of respective item, is |
A. |
Cleats | B. |
Brackets | C. |
Bolts | D. |
Distance separators | E. |
All the above. |
Answer: Option E
Explanation:
|