Discussion Forum : Construction Management - Section 2 (Q.No. 1)
1.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
Discussion:
8 comments Page 1 of 1.
Saima said:
8 years ago
The independent float is the excess of minimum available time over the required activity duration.
Guriya said:
5 years ago
(LS-Es)-di = independent float.
So A option is correct.
So A option is correct.
Yehia said:
9 years ago
What is independent float of the activity?
Vijay said:
3 years ago
t2-(t1+t) is the correct answer for this.
(1)
Lokanath said:
4 years ago
I think here it is (t2 - t1) - t.
(2)
Sachin said:
8 years ago
The correct answer is t2-(t+t1).
Getachew said:
7 years ago
How to solve this? Explain me.
Hariram Rimal said:
7 years ago
Here Ej-Li-d.
So, (t2-t1)-t.
So, (t2-t1)-t.
(1)
Post your comments here: