Discussion Forum : Construction Management - Section 2 (Q.No. 1)
1.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
8 comments Page 1 of 1.

Vijay said:   3 years ago
t2-(t1+t) is the correct answer for this.
(1)

Lokanath said:   4 years ago
I think here it is (t2 - t1) - t.
(2)

Guriya said:   5 years ago
(LS-Es)-di = independent float.
So A option is correct.

Hariram Rimal said:   7 years ago
Here Ej-Li-d.
So, (t2-t1)-t.
(1)

Getachew said:   7 years ago
How to solve this? Explain me.

Sachin said:   8 years ago
The correct answer is t2-(t+t1).

Saima said:   8 years ago
The independent float is the excess of minimum available time over the required activity duration.

Yehia said:   9 years ago
What is independent float of the activity?