Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 1)
1.
If t is the duration of an activity, t1 is the latest finish possible moment of its preceding activity and t2 is the earliest start possible moment, the independent float of the activity is
(t1 - t2) - t
t - (t1 - t2)
(t1 + t2) - t
t + (t1 - t2)
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
8 comments Page 1 of 1.

Yehia said:   9 years ago
What is independent float of the activity?

Saima said:   8 years ago
The independent float is the excess of minimum available time over the required activity duration.

Sachin said:   8 years ago
The correct answer is t2-(t+t1).

Getachew said:   7 years ago
How to solve this? Explain me.

Hariram Rimal said:   7 years ago
Here Ej-Li-d.
So, (t2-t1)-t.
(1)

Guriya said:   5 years ago
(LS-Es)-di = independent float.
So A option is correct.

Lokanath said:   4 years ago
I think here it is (t2 - t1) - t.
(2)

Vijay said:   3 years ago
t2-(t1+t) is the correct answer for this.
(1)