Discussion Forum : Construction Management - Section 2 (Q.No. 23)
23.
Pick up the incorrect statement from the following:
Discussion:
6 comments Page 1 of 1.
Gyan chaudhary said:
8 years ago
Option C is incorrect I think.
Lokesh said:
6 years ago
Yes, Option C is the incorrect definition.
Hamza said:
5 years ago
No, option C is correct.
The formula of Total float is:
TF=LF-EF or LS-ES.
Here,
TF: Total float.
LF: Latest finish time.
EF: earliest finish time.
LS: Latest start time.
ES: Earliest start time.
The formula of Total float is:
TF=LF-EF or LS-ES.
Here,
TF: Total float.
LF: Latest finish time.
EF: earliest finish time.
LS: Latest start time.
ES: Earliest start time.
Subha prakash Sahoo said:
4 years ago
Actually, option D is wrong because in the case of free float it is the maximum time that can be delayed without affecting the start of the successor activity.
Thus it is Est of successor-Est of predecessor-duration.
Thus it is Est of successor-Est of predecessor-duration.
(1)
Tarkraj said:
3 years ago
Option C is incorrect because free float=EF-ES-duration of the same activity.
Kiran said:
1 year ago
Both D and C are incorrect.
I think here option E to be correct,
option C- (TF=Latest start time of successor activity - earliest start time of activity - duration).
Option D- (FF=Earliest Finish time -Earliest start time of an activity - duration of activity).
I think here option E to be correct,
option C- (TF=Latest start time of successor activity - earliest start time of activity - duration).
Option D- (FF=Earliest Finish time -Earliest start time of an activity - duration of activity).
Post your comments here: