Pick up the incorrect statement from the following:
The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity
The difference between the maximum time available for the job and actual time it consumes, is called total float
The difference between the latest start time and earliest start time of an activity, is called total float
The difference between the earliest finish time of an activity and the earliest start time of its successor activity, is called free float of the activity
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
6 comments Page 1 of 1.

Kiran said:   1 year ago
Both D and C are incorrect.

I think here option E to be correct,

option C- (TF=Latest start time of successor activity - earliest start time of activity - duration).

Option D- (FF=Earliest Finish time -Earliest start time of an activity - duration of activity).

Tarkraj said:   3 years ago
Option C is incorrect because free float=EF-ES-duration of the same activity.

Subha prakash Sahoo said:   4 years ago
Actually, option D is wrong because in the case of free float it is the maximum time that can be delayed without affecting the start of the successor activity.

Thus it is Est of successor-Est of predecessor-duration.
(1)

Hamza said:   5 years ago
No, option C is correct.

The formula of Total float is:
TF=LF-EF or LS-ES.

Here,
TF: Total float.
LF: Latest finish time.
EF: earliest finish time.
LS: Latest start time.
ES: Earliest start time.

Lokesh said:   6 years ago
Yes, Option C is the incorrect definition.

Gyan chaudhary said:   8 years ago
Option C is incorrect I think.