Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 2 (Q.No. 33)
33.
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
20
25
35
15
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
17 comments Page 2 of 2.

Assumi said:   4 years ago
For latest occurence time, backward pass method is used and for earliest expected time, forward pass method is used.

Sadulla said:   5 years ago
Right, Thanks @Kajal.

Dan said:   7 years ago
You are right @Kajal Tomar.

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Rituraj said:   10 years ago
Is this is possible that pessimistic time can be less than optimistic time? Please answer this.