Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 2 (Q.No. 33)
33.
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is


Discussion:
17 comments Page 2 of 2.
Assumi said:
4 years ago
For latest occurence time, backward pass method is used and for earliest expected time, forward pass method is used.
Sadulla said:
5 years ago
Right, Thanks @Kajal.
Dan said:
7 years ago
You are right @Kajal Tomar.
Amjad said:
10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?
Amjad said:
10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?
Amjad said:
10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?
Rituraj said:
10 years ago
Is this is possible that pessimistic time can be less than optimistic time? Please answer this.
Post your comments here: