33.
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
20
25
35
15
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
17 comments Page 1 of 2.

Naveen B said:   1 decade ago
{Op time + (4 * Most lik time) + pess time}/6.

i.e {15+(4*28)+21}/6 which is equal to 24.6666 = 25.
(1)

Rituraj said:   10 years ago
Is this is possible that pessimistic time can be less than optimistic time? Please answer this.

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Amjad said:   10 years ago
Then what is the contractual obligation 75 and latest occurrence is 2?

Pranab said:   9 years ago
It is considering 1-2, the contractual obligation 75 and latest occurrence is 2. It is considering latest occurrence 1-2.

{PT + (4 x MLT) + OT}/6.
i.e {15+(4x28)+21}/6 which is equal to 24.66.

But, contractual obligation 75,
From event 1-2, 2-3, and 3-4 total 3 duration time,
so, time duration to reach 1-2 is 75/3 = 25,
25>24.66.
Due to contractual obligation, the time will be the greater one
Ans = 25.
(5)

Kajal Tomar said:   7 years ago
Latest occurrence time calculated from backward pass method.

Therefore TL of event 4 is 75 given;
Now( 75- (TE of 3-4) - (TE of2-3)),
TE =( opt time + 4 *most lik time + pess time) /6.
75 - (15) - (35) = 25 i.e TL of event 2 i.e asked.
(6)

Dan said:   7 years ago
You are right @Kajal Tomar.

AKHILA said:   6 years ago
Thanks @Kajal Tomar.

Sadulla said:   5 years ago
Right, Thanks @Kajal.