The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is
19
14
24
None of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
8 comments Page 1 of 1.

Dinesh gupta said:   3 years ago
1-2=>(3+(4*4)+5)/6 = 24/6 = 4.
2-3=>(5+(7*4)+9)/6 = 42/6 = 7.
3-4=>(6+(8*4)+10)/6 = 48/6 = 8.
(4)

Sabina said:   5 years ago
@Zahid.
Activity 3-4 calculation is wrong by;
Expected time= 6 + 4 * 8 + 10/6 = 8.

Lalitha said:   7 years ago
Nice explanation. Thank you @Zahid.

Dev Kumavat said:   7 years ago
Thank you @Zahid.

Uttu said:   7 years ago
@Subha.

Activity 4 cannot be started without activity 1 2 & 3.

So, 19 is correct.
(3)

Subha Annadurai said:   7 years ago
According to me, 3-4=>(6+(8*4)+10)/6 = 8.

Bhai said:   9 years ago
Nice @Zahid.

Zahid said:   1 decade ago
Using PERT formula for each activity. Add the value obtained to get 19.

Activity 1-2 => (3+(4*4)+5)/6 = 4.

2-3 =>(5+(7*4)+9)/6 = 7.

3-4 => (6+(4*4)+10)/6 = 8.

4+7+8 = 19.