Discussion Forum : Construction Management - Section 1 (Q.No. 7)
7.
In the given figure, the network of a project represents


Discussion:
12 comments Page 2 of 2.
Gulshan k said:
7 years ago
@Muhammad.
The digit written on an arrow represents the time required to complete that activity.
The digit written on an arrow represents the time required to complete that activity.
Bastenga said:
6 years ago
Right, Thanks @Sumit.