In the given figure, the network of a project represents
activity of an excavation of a footing
activity of an excavation which starts at event No. 1 and ends at even No. 2
activity of excavation which takes 8 units of time
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
12 comments Page 2 of 2.

Bastenga said:   6 years ago
Right, Thanks @Sumit.

Shubham Anadkat said:   4 years ago
"Excavation Of Footing" indicates the Activity. So here no matter there is an arrow or not.