For completion of a project, the critical path of the network represents
Discussion:
40 comments Page 4 of 4.
Anonymous said:
9 years ago
The answer is correct. No doubt that critical path is always taken as the maximum time taken but it signifies that all the activities will be finished in that time and for the project to be considered as complete that time will be minimum.
Samson KP said:
9 years ago
The critical path is the longest duration path through a network diagram and determines the shortest time to complete the project.
Therefore the answer is option A.
Therefore the answer is option A.
GUNNA SATISH said:
9 years ago
Answer is wrong. Correct answer is maximum time.
Prateek bansal said:
9 years ago
CPM is based on cost optimisation, so the answer may be minimum cost.
Robert said:
9 years ago
Well, I think the gist of the question here is for completion of a project, thus making the critical path the minimum time possible.
Rajashekhar Hallur said:
9 years ago
Yes, its maximum duration of activities and hence its maximum time.
Santosh said:
9 years ago
Surely the answer should be B. maximum time.
Rajesh said:
1 decade ago
Me to confused the answer must be B.
Navin said:
1 decade ago
Correct answer option B, because critical path is the longest path.
Vrushik said:
1 decade ago
How? I think the answer is B. As the total time in critical path is maximum.