Civil Engineering - Construction Management - Discussion
Discussion Forum : Construction Management - Section 1 (Q.No. 13)
13.
A Milestone chart
Discussion:
13 comments Page 1 of 2.
Akshay said:
8 years ago
What does it shows?
Harshit said:
8 years ago
@Akshay.
It shows Start and end point in the project.
It shows Start and end point in the project.
Srinukota19 said:
8 years ago
I think its A B C tree are correct.
Akshay m s said:
7 years ago
It is Significant event of a project.
Aloysius k said:
7 years ago
It shows expected completion dates of specific tasks.
Memon said:
7 years ago
Can someone tell us the exact Answer with the explanation.
(1)
Biyanka said:
7 years ago
It gives the status of a group of activities in a project. That means. It shows the starting date, expected completion date, rescheduled date, the actual completion date of each group of activity which is known as a milestone.
And this milestone chart is prepared in excel sheet.
And this milestone chart is prepared in excel sheet.
Rahul said:
6 years ago
In every activity there are certain key events which mark the completion of a certain portion of the main activity, these key events are Milestones.
Example- If construction of Footing is main activity then Excavation is the first milestone
PCC laying is 2nd.
Formwork is 3rd.
Reinforcement 4th.
Concreting is 5th.
Example- If construction of Footing is main activity then Excavation is the first milestone
PCC laying is 2nd.
Formwork is 3rd.
Reinforcement 4th.
Concreting is 5th.
(1)
Romi said:
5 years ago
They are tools used to mark specific points along a project timeline.
V V R said:
5 years ago
In a milestone, chart milestones are generally used to show the completion of different sub-activities and also the progress of a project can be shown.