Civil Engineering - Construction Management - Discussion

Discussion Forum : Construction Management - Section 1 (Q.No. 13)
13.
A Milestone chart
shows the interdependencies of various jobs
depicts the delay of jobs, if any
points outgoing ahead of schedule of jobs, if any
none of these.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
15 comments Page 2 of 2.

Karan said:   4 years ago
Yes, in Milestone chart,

Greenline shows Work in time.
Black- Intended work.
Red- Behind schedule work.

Also shows the completion of sub-activities hence it is more advance than Bar chart.

If none of this option is correct then what's the difference between Milestone and Bar chart?

Hence, 4th option should be All of these.
(1)

MUHAMMAD NABI said:   3 years ago
All the given option is right. So the answer is All of these.
(1)

Devesh Sahu said:   1 year ago
It is a modification over the original Gantt (Bar) chart. Milestones are key events of main activities represented by the bar.
(3)

Agha Bilal said:   4 months ago
None of these is the correct answer!

All the statements given relating to the Milestone Chart are incorrect here.

Shah said:   4 weeks ago
Actually, milestone is event start of the activity or end of the activity and it has zero time, so all the above options are incorrect.


Post your comments here:

Your comments will be displayed after verification.