Civil Engineering - Concrete Technology - Discussion

Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
7 days for beam soffits
14 days for bottom slabs of spans 4.6 m and more
21 days for bottom beams over 6 m spans
2 days for vertical sides of columns
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 3 of 4.

Richa Pandey said:   9 years ago
Nice, thanks for all your ideas.

Rustam Tomar said:   9 years ago
As per IS:456, Removal of formwork for vertical columns is between 16-24 hrs.

RAJENDRA KUMAR said:   9 years ago
Minimum 10hours for vertical side columns but curing is regular 2 time/day, so 14 days.

Ajay said:   9 years ago
Can you guys explain it correctly.

Sucharit Barua said:   10 years ago
Option D wasn't correct because all vertical form work of column, wall and beams should be removed within 16-24 hours.

Satani Mohit said:   10 years ago
21 days is enough of durability for concrete.

Pawan verma said:   10 years ago
What is soffits beam?

Aswin said:   10 years ago
Nice. Thanks for your ideas :-).

NILLA RAVITEJA said:   1 decade ago
30 hours is best for removal of form work for vertical sides of columns.

Mithilesh sah said:   1 decade ago
1 days or 24 hours for vertical side.