Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
7 days for beam soffits
14 days for bottom slabs of spans 4.6 m and more
21 days for bottom beams over 6 m spans
2 days for vertical sides of columns
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 1 of 4.

Gaurav said:   6 years ago
Soffit is bottom part of beam.
(3)

Hamza ayoub said:   6 years ago
Beam soffit is bottom side of beam.
(2)

Malladi said:   6 years ago
What is beam soffit?

Aliraza said:   6 years ago
Thanks for all.

Archna said:   6 years ago
Thanks all.
(2)

Kumar saurab said:   7 years ago
What are the different types of cement?
(2)

Jishnu Sarkar said:   7 years ago
What is form work?
(1)

Mjit said:   8 years ago
What is the form removal time period for roof slab?
(1)

Golam Murtoza said:   8 years ago
- Removal Time Period.

Walls, columns and vertical sides of beams 24 to 48 hours as may be decided by the Engineer-in-charge.
- Slabs (props left under) 3 days.
- Beam soffits (props left under) 7 days.
- Removal of props to slabs (Spanning up to 4.5 m) 7 days.
- Removal of props to slabs (Spanning over 4.5 m) 14 days.
- Removal of props to beams and arches (Spanning upto 6 m) 14 days.
- Removal of props to beams and arches (Spanning over 6 m) 21 days.
(14)

MD Shekhar said:   8 years ago
A) Modification: *****7 days for beam soffits( props left as in their position).
(3)