Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
Discussion:
32 comments Page 1 of 4.
Younas ahmad said:
1 decade ago
14 days for bottom slabs of spans 4.6 and more.
Name muhammad israr said:
1 decade ago
Minimum 14 days required for slabs and bottom.
MATHIALAGAN said:
1 decade ago
Even 7 working days With props left under the external temperature 35 degree centigrade span up to 6 m.
Mithilesh sah said:
1 decade ago
1 days or 24 hours for vertical side.
NILLA RAVITEJA said:
1 decade ago
30 hours is best for removal of form work for vertical sides of columns.
Aswin said:
10 years ago
Nice. Thanks for your ideas :-).
Pawan verma said:
10 years ago
What is soffits beam?
Satani Mohit said:
10 years ago
21 days is enough of durability for concrete.
Sucharit Barua said:
10 years ago
Option D wasn't correct because all vertical form work of column, wall and beams should be removed within 16-24 hours.
Ajay said:
9 years ago
Can you guys explain it correctly.