Civil Engineering - Concrete Technology - Discussion
Discussion Forum : Concrete Technology - Section 1 (Q.No. 3)
3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
Discussion:
32 comments Page 2 of 4.
RAJENDRA KUMAR said:
9 years ago
Minimum 10hours for vertical side columns but curing is regular 2 time/day, so 14 days.
Rustam Tomar said:
9 years ago
As per IS:456, Removal of formwork for vertical columns is between 16-24 hrs.
Faiz Khan said:
9 years ago
According to my thought, 7 day for beam soffits is sufficient.
(1)
Richa Pandey said:
9 years ago
Nice, thanks for all your ideas.
Engg chanchal said:
9 years ago
Beam slab and column casting in 20-24 hours remove at form work.
Chinny said:
8 years ago
What is meant by beam soffit?
Shaikrehaman said:
8 years ago
Soffit means the bottom surface of the beam.
Tadesse said:
8 years ago
Vertical form work of column be removed within 16-24 hours.
Sachin Kadam said:
8 years ago
Only 1 day required for vertical members.
Karmveer kohli said:
8 years ago
If all of is not in option then which is right answer?