Ravi Kumar Maddheshiya said:
8 years ago
Can you explain soffit beam?
Binay said:
8 years ago
I believe beam soffit means the cantilever portion of the beam. It is just a hunch, please correct me if I am wrong.
MD Shekhar said:
8 years ago
A) Modification: *****7 days for beam soffits( props left as in their position).
(3)
Golam Murtoza said:
8 years ago
- Removal Time Period.
Walls, columns and vertical sides of beams 24 to 48 hours as may be decided by the Engineer-in-charge.
- Slabs (props left under) 3 days.
- Beam soffits (props left under) 7 days.
- Removal of props to slabs (Spanning up to 4.5 m) 7 days.
- Removal of props to slabs (Spanning over 4.5 m) 14 days.
- Removal of props to beams and arches (Spanning upto 6 m) 14 days.
- Removal of props to beams and arches (Spanning over 6 m) 21 days.
Walls, columns and vertical sides of beams 24 to 48 hours as may be decided by the Engineer-in-charge.
- Slabs (props left under) 3 days.
- Beam soffits (props left under) 7 days.
- Removal of props to slabs (Spanning up to 4.5 m) 7 days.
- Removal of props to slabs (Spanning over 4.5 m) 14 days.
- Removal of props to beams and arches (Spanning upto 6 m) 14 days.
- Removal of props to beams and arches (Spanning over 6 m) 21 days.
(14)
Mjit said:
8 years ago
What is the form removal time period for roof slab?
(1)
Jishnu Sarkar said:
7 years ago
What is form work?
(1)
Kumar saurab said:
7 years ago
What are the different types of cement?
(2)
Archna said:
6 years ago
Thanks all.
(2)
Aliraza said:
6 years ago
Thanks for all.
Malladi said:
6 years ago
What is beam soffit?