3.
Under normal conditions using an ordinary cement, the period of removal of the form work, is :
7 days for beam soffits
14 days for bottom slabs of spans 4.6 m and more
21 days for bottom beams over 6 m spans
2 days for vertical sides of columns
all the above.
Answer: Option
Explanation:
No answer description is available. Let's discuss.
Discussion:
32 comments Page 4 of 4.

Name muhammad israr said:   1 decade ago
Minimum 14 days required for slabs and bottom.

Younas ahmad said:   1 decade ago
14 days for bottom slabs of spans 4.6 and more.